The schedule for processing of Rule-38 March 2026 cycle has been finalized and is communicated as under for necessary action by all concerned:
Transfer requests from 01.09.2025 to 28.02.2026 will be considered for processing
Activity
Number of approximate working day required
Timelines
Time for preliminary activities
7 to 10 days
08.05.2026 to 15.05.2026
Vacancy Capturing by DO/CO/MMS/Other Units.
5 days
18.05.2026 to 22.05.2026
Result Generation / Request processing
7 days
23.05.2026 to 29.05.2026
Publishing of Trial Result
2 days
01.06.2026 to 02.06.2026
Provisional Allotment list
3 days
03.06.2026 to 05.06.2026
Final Approved transfer order publishing date
1 days
06.06.2026
Reliving and Joining
As per existing guidelines.
2. All Circles/Units are requested to ensure timely completion of all activities within the prescribed timelines so that the transfer cycle may be completed smoothly and without delay.
3. It may also be ensured that any technical issue pertaining to applications is forwarded to CEPT only through the proper channel/support desk after due verification at the Circle/Division level.
4. Further, issues relating to transfer requests for the period 01.09.2025 to 28.02.2026 shall be entertained only if received through the concerned authority before the prescribed cut-off date. No changes/modifications in transfer requests shall be permitted thereafter.